Welcome to the Meany Work Party Page

if you have been wondering what it takes to keep Meany going, well come to one of the fall Work Parties in the fall and see what it takes. The cost to you -- is absolutely nothing -- well some work would is required.

We offer mid-week and weekend workparties, If you want to attend any of these simply click on work parties, pick the weekend and sign up.




Work Party Reports

Please click on any of the topics below to go directly to that section or simply scroll down


July Report

Attendees

The following individuals were at the work party: - THANK YOU ALL FOR COMING !!!!!
  1. Doug Damm
  2. John Rice
  3. Bob Grass
  4. Tom VanDevanter
  5. Dan Solomonson
  6. Don Finrow
  7. Phil Christy
  8. Mike Lonergan
  9. Patti Polinsky
  10. Dave Claar
  11. Ray Nelson
  12. Phyllis Nelson
  13. Emilio Marasco
  14. Jim Fahey
  15. Linda Marasco
  16. Christopher Marasco
  17. Juliana Marasco
  18. Avner Aharoni
  19. Nimroul Agmon & son Vri
  20. Dan Nord
  21. Jim Noyes
  22. Tom Dunston


Intro

First, as with any event at Meany, a cook and "galley slaves" are required to feed the hungry masses, well at this work party, the cook was Don Finrow and the galley slaves were the Harkness/Marasco clan.

Second, I'm sure most individuals have heard of the committee talk about the fossils and how the lodge is indebted to them for all of there tireless work that they put in, well during this work party, we manage to get a picture of a bunch of them lounging around the lodge


Galley Slaves

from left to right, Mike Lonergan, Phil Christy,
Don Finrow and Bob Grass


















Road grading and creek crossing repair

The backhoe was delivered as scheduled on Thursday. It was used to repair the water damage up the hill to the Railroad tracks and did some straightening up of the creek crossing. Someone had fixed up the creek crossing about an hour before we got at it but left it a little rough in places.
Webmaster note: I was up at Meany for the MOFA class weekend in June, and I can tell you that the creek crossing and road then was extremely rough, mostly 4x4 were only able to get to the lodge. In July I was able to drive my mini-van to the lodge.


Lodge foundation

Lodge concrete foundation wall was exposed, treated with a sealant, a new 6 inch drain pipe placed on the footing and backfilled with drain gravel. Because we did not get the last truck load of gravel until late Monday we did not finish the back fill. When the final grading and backfill is complete, we will put some logs on the brink of the slope going into the Lodge to keep cars from getting to close to the drop off into the foundation.


Excavation almost done,
Mike Lonergan inspecting,
Bob Grass handling the backhoe

Linda & Emilio applying foundation sealant

Job minus last gravel load & log bumper
























Campus grading

The dirt and rocks removed was used to fill the areas around the Cat House and Zoo. These areas received their final dressing and are believed need no further work, in prep for the leveling, various miscellaneous equipment was moved away from Zoo


Part of the dirt/rocks used for the grading

Juliana & Emilio moving grousers parts
in prep for grading around Zoo

Loader moving the dirt/rocks
























Water Supply Dam repair

The leak at the water supply dam was fixed. The dam was extensively repaired in several aspects rather that replaced. Replacing it turned out to be just too big a task at this time.

It should be noted that when the dam was filling that there was some minor leakage. It is not known where the leakage is taking place (it is not obvious). The dam did mostly fill and was supplying water to the 1500 gallon storage tank. The hose and water collection arrangement was left in place just in case there are further problems that develop with the reservoir. It may become necessary to further seal the bottom of the reservoir with a clay substance or some other method.

For now and some time into the future it appears that the dam is structurally sound and should serve our needs fine (it may not look as pretty as new). What is in question is the sealing of the bottom and around the ends of the dam. Time will tell on this point.


Water drained and end boards removed

Doug & John placing 2 X 12
board across the top of the dam

John working on dam edge
























Furnace inspection & fire wood

The shrouds around the wood furnace were removed and the furnace inspected. The shape of the furnace was found to be in better condition that it was feared it would be. Based on what we have observed we do not feel the furnace needs to be replaced at this time. What needs to be done is to replace the shrouds with new, replace the elbows and horizontal flue pipe along with replacement of blower used to draw off heat from the furnace and direct into the basement.

Collecting and splitting fire wood was carried out. The trees down in the swamp were cut up, mostly split and hauled to the lodge. The trees behind the Tow Hut that were down have been cut up and hauled to the Lodge.

There are limbs that still need to be chipped as a result of the wood gathering. A lot of limbs were chipped.


Image of furnace

Image of furnace

Phil and Tom (yes of Tom-Cat fame)
splitting wood


















Electrical Work

The electrical work on the tows started. The old switch gear was removed; trenches were dug for the new electrical runs to the Turtle and Super Worm Tow. The conduit was placed in the trenches. More conduit parts are needed and will be acquired and use at the next work party.
(Note: the trenches may be back filled at any time except for the last 50 feet of the phone line run toward the Lodge - there is still work to do on that end and the conduit needs to remain free there).


Trench from lodge to tow hut

Conduit in trench

trench in back of tow hut

















Other tasks

I apologize for not having pictures of the other activities, but here is what was also done

Top of page

August Report

Men's dorm remodel

Early in August the remodeling of the Men's Dorm was started; yes Norm, Deb and Alex, out of the kindness of their hearts, and not wanting to hear the begging and pleading of the Men, decided that the Men Dorm needed an overhaul. So Out came all the old beds and on went new paint. Sadly no pictures. This remodel will continue with new carpet and beds.


August midweek workparty

Attendees

The following individuals were at the work party: - THANK YOU ALL FOR COMING !!!!!
  1. Doug Damm
  2. Dan Solomonson
  3. Phil Christy
  4. Mike Lonergan
  5. Ray Nelson
  6. Deborah Cole
  7. Tom Dunston


Tasks Accomplished


Meany Engineering

We always talk about the "Meany Way" of doing things, some may think of it as "Rube Goldburg", but I rather call it "Engineering on the Fly". Here are two examples of how things can be reinvented to serve a purpose at Meany

Clothes dryer

I'm sure all of you have noticed that "big green box" that pumps out hot air to dry your clothes. Well during the inspection of the furnace, it was decided that it too needed to be replaced, well someone, think it was Mike Lonergan, suggested that we may be able to make use of a used Furnace carcass. Ray Nelson found a very understanding furnace company near his home, and they graciously gave us one. The first image below shows it at the furnace company and second image has it installed at Meany. All we need to do is to install the motor and "squirrel cage" and we have a new blower

High Tech Milling Machine

For everyone's information, there is a master wooden pulley for each of our tows. For example, the biggest, for Mach, stands about 4' in diameter and has a thickness of around 6 inches. Well after many years of successful service, they eventually begin to wear out. The problem, in replacing them, is you can't simply go down to the local hardware store and pick up a replacement. You need to build one. Mike Lonergan took it upon himself to do just that for Worm. So for everyone's edification, in the third image below, I present the one of a kind "Meany Milling Machine", now not tooo many oohs and aahs















Top of page

September Report

Weekend Workparty - Sept 11th - 12th

The first weekend workparty had real intimate group, some of the fossils (Ray Nelson and Doug Damm) were up sizing what was to be accomplished during the coming week, the Harkness-Marasco family, Andy Smith, Phil Christy and Jerry Thompson. Ray Hecox cooked some killer pork chops for dinner and we sampled the Mushroom Risotto that will be served Mushroom Weekend.


Carpet

Andy and Jerry manage to get the carpeting out of the men's dorm and both stairwells to facilitate replacing it on the following Monday. Chuck and Christopher did the final vacuuming. You should have seen the amount of "dust and assorted stuff" the shop vac picked up. Deb Cole gave us her day off, Monday, to come and supervise the carpet installation. Webmaster note: the carpet is fantastic, we will probably require feet wiping before you go up the stairs


Men's Dorm remodel

Chuck and Christopher sawzalled the old iron mattresses out of the wooden bed frames. Phil and James got started rebuilding some of the bunks while Juliana and Linda primed the frames and new bed platforms plywood Webmaster note: After seeing what Juliana looked like when we finished, I'm wondering what got most of the paint - her or the wood


New Meanyite

During the morning, a vehicle came up the drive with someone we didn't know. He stopped and told Chuck that he had always heard about Meany and wanted to come and see if he could find it. (He is a volunteer for Washington trail association) - well he not only looked around, he stayed for lunch and pitched in and split wood !!!! He stated that we will see him in the winter. - new Meanyites are acquired by the strangest means


Midweek Workparty - Sept 14th - 16th

The following individuals attended:

  1. Doug Damm
  2. John Rice
  3. Bob Grass
  4. Tom VanDevanter
  5. Dan Solomonson
  6. Don Finrow
  7. Tommy Dunstan
  8. Phil Christy
  9. Mike Lonergan
  10. Ray Nelson
  11. Deborah Cole


Remodeling

The carpet was installed in the Men's dorm, and stairwell from the third floor to the basement. The doors that no longer fit were shortened to fit and the old carpet was haulled to the dump. More of the men bunks were rebuilt.


Deb inspecting the job

Phil working on beds

More bed work
















Dam Repair

The leak in to dam was addressed with placing Sodium Bentonite in the leaking area. The leak was reduced considerably but still needs more work. Additional Sodium Bentonite will be applied at the at the next opportunity when we can have sufficient time to flush the reservoir.


Furnace

Furnace shroud and new flue pipe were installed. The furnace is now in service. The basement "dryer" fan was installed but not wired up. It will be wired to have multiple speed switch so that one can select how much heat you want in the basement.


John working on Furnace

Work completed

Another view
















Moose cargo carrier

Last year Meany purchased another sno-cat, which we named "Moose". It was bought to help off-load TomCat. It was decided that we needed a cargo carrier to do that. It is almost finished. Last thing to install will be stairs to help loading and unloading


Moose without carrier

Carrier installed

Dan and Tom putting finishing touches
















Others


Weekend Workparty - Sept 26th - 27th

Almost 20 people at dinner Sat. night. And there is still a ton of work to do. So this is what got done

We also sampled two possible entrees planned for our Italian themed dinner. Yes Emilio has been talking about it for awhile, now time to produce..... for Saturday dinner, did a Chicken Caccittore that was hard not to over indulge and for Sunday lunch, Minestrone

Top of page

October Report

Weekend: Oct 11th - 12th

What got accomplished

The Turtle tow rope replacement and splicing got finished and the drive guards replaced. And before I continue with the list, here are a series of pictures taken by the world reknown (well maybe not yet) Meany resident phtographer Amy Deyerle-Smith. In between mowing down South, she took pictures of the splicing of Turtle. Now was she biased in that her Dad (Greg Smith) was helping Jim Fahey - who am I to judge.


Jim pulling on the rope to get tension off

Greg feeding the fid to Jim

Weaving of turtle tow continues












MidWeek: Oct 13th - 15th

The following individuals were in attendance during a very cold and wet 3 days

  1. Doug Damm
  2. John Rice
  3. Bob Grass
  4. Tom VanDevanter
  5. Dan Solomonson
  6. Tom Dunstan
  7. Mike Lonergan
  8. Ray Nelson
  9. Patti Polinsky
  10. Dave Claar
  11. Brian Johnson
  12. Jay Johnson
  13. Deborah Cole

Here's what we got done:


Tom D & New switch in Tow Hut


John working on oven









Jay & Brian Johnson working on
basement door






Patti remodeling Ladies camode







Top of page